Report: Legacy Tools & Hiring Top Concerns Amid Construction Boom

The “Construction Tech and Workforce Report” reveals that while most construction professionals want greater team involvement in scheduling, many face talent shortages and outdated tools, highlighting the need for simpler, collaborative planning solutions.

Today, Planera announced the findings of the “Construction Tech and Workforce Report” which looked at how construction professionals are using technology to plan and schedule their projects. 

What we found was that the vast majority of those surveyed (78%) said their business would benefit from having more team members involved with the scheduling process (See Figure 1).

Bar graph showing responses to whether business would benefit from more people in the scheduling/planning process
Figure 1: Would your business benefit if more people were involved in the scheduling and planning process?

However, a full 37% of respondents cited difficulties with finding employees with sufficient construction scheduling and planning experience (See Figure 2).

Bar graph showing hiring challenges
Figure 2: What best describes your hiring challenges?

In addition, 2 out of 3 construction decision-makers said their current planning software is complex and challenging to use (See Figure 3).

Pie chart showing the general ease of use of planning software
Figure 3: Describe the ease of use for the planning software your company uses.

The timing of the survey, which asked 200 United States construction managers and executives about their experience utilizing technology for construction planning efforts, is particularly important as US construction spending and hiring is going strong. In fact, construction spending advanced 3.5% on a year-on-year basis over the summer, exceeding expectations. On top of this, the American Institute of Architects released their annual Consensus Construction Forecast, which projects that nonresidential construction spending will increase by 20% this year.  

Amid this continued trend of increased construction spending, contractors are struggling to keep pace with new bids due to outdated and complex planning systems. These inefficient systems serve as a barrier to entry for these contractors and prevent them from securing projects (see Figure 4), properly managing timelines, and identifying the correct amount of necessary manpower and supplies.

Pie chart showing the percentage of bids lost due to insufficient planning tools
Figure 4: How many bids does your organization lose due to insufficient planning tools?

Having an easy-to-use and collaborative scheduling tool will better position construction pros to not only be prepared for bids and schedules for projects, maintaining both efficiency and profitability, but also prevent them from having to hire employees with a specialized skill set to manage this technology. 

Here are some additional key findings from the survey:

Talent Gaps: Only 38% of respondents said they believe they are sufficiently staffed to handle an influx of new construction projects, but plan to hire ahead of a potential spike in demand (see Figure 5).

Bar graph showing responses to staffing for an influx of IIJA federal funds
Figure 5: Are you sufficiently staffed for new construction projects?

Construction Companies Look to Improve Human Capital and Infrastructure: More than half of respondents (54%) say they need to recruit talented people and improve the technology infrastructure to execute new projects. 17% say the current technology does not keep pace with current needs, and 27% say it’s a challenge finding and recruiting people with the right skills to execute projects. See Figure 6.

Bar graph showing skills needed to expand for new projects
Figure 6: What skills does your company need to expand?

Investments in Planning Tools are a Priority for Construction Pros: In today’s booming construction market, 42% of respondents are “definitely” prioritizing investments in planning tools, while 38% marked “probably.” See Figure 7.

Bar graph showing responses to prioritizing investments in construction planning tools
Figure 7: Are you prioritizing investments in scheduling and planning tools?

Resources for modern 
construction professionals

See all posts →
construction cpm schedule update

Articles

A Step-by-Step Guide on How to Update a Construction CPM Schedule

Read More

near critical path construction

Articles

Why Near-Critical Paths Matter in Construction Project Scheduling

Read More

resource loaded construction schedule

Articles

How to Build a Resource-Loaded Construction Schedule: Complete Guide

Read More

A Step-by-Step Guide on How to Update a Construction CPM Schedule
Why Near-Critical Paths Matter in Construction Project Scheduling
How to Build a Resource-Loaded Construction Schedule: Complete Guide
De-Risk the Supply Chain, Keep Procurement on the Critical Path
Protecting the Pro Forma: Why Owners Need Direct Eyes on the Capital Improvement Schedule
The Complete Guide to Data Center Construction From Planning to Turnover
How Long Does Data Center Construction Take? Timeline, Phases, and Challenges
AI Agents for Construction: Use Cases, Benefits and Examples
6 Best AI Construction Scheduling Tools in 2026
Legacy Tools 
Weren’t Built
for Data Center Construction
Planera Names Stephen Archibald Chief Financial Officer
How to Use AI in Construction: Practical Use Cases for Construction Teams
What's New in September
Five Takeaways from the Built for the AI Boom: Data Center Webinar
How to Conduct Delay Analysis for Construction Projects: Methods, Claims and Best Practices
De-Risking the Supply Chain: How Visual Sequencing Keeps Long-Lead Procurement on the Critical Path
What's New in Planera: July 2026
How to Develop a Commercial Construction Project Schedule
What's new in Planera: August 2026
How Construction Schedule of Values Helps Manage Project Costs and Payments
Construction Firms Face Autumn Microsoft Project Retirement Deadline
The Scheduler's Playbook
The Blueprint for Project Success: Why Collaborative Planning and AI are Redefining Construction Scheduling
How Construction Schedule Levels Improve Project Planning and Execution
Moving Beyond the Gantt Chart
Flipping the Construction Profit Equation
Making Schedules Accessible
How to Create a Construction Master Schedule and Manage a Project Timeline Successfully
Every Project You've Ever Seen Run Late Was Scheduled on Software from 2007
Construction Milestone Schedule: How to Plan Key Project Dates and Keep Projects on Track
The High Cost of Inaction: Why Sticking with Legacy Scheduling is Eroding Contractor Margins
What's new in Planera (June 2026): schedule changes with Manny, searchable notes, and more
Construction Fast Tracking: What It Is, When to Use It, and What Can Go Wrong
Lean Construction Scheduling: Principles, Techniques, and Benefits
Pull Planning in Construction: Process, Benefits, and Examples
Construction Sequence Plan: How to Sequence Work for Better Project Flow
9 Best Touchplan Alternatives for Construction Project Management in 2026
9 Best Outbuild Alternatives for Construction Project Management in 2026
Critical Path Method (CPM) in Construction: A Full Guide
What's New in Planera: May 2026
The Best Procore Alternatives for Construction Scheduling
Moving From
Legacy Tools to Modern CPM, the Complete Guide for Modern Construction Teams
Elevating Construction Success: The Planera Support Advantage
The Shift from Oracle P6 to Planera: Why Leading Contractors are Choosing Collaborative Scheduling
Lookahead Scheduling in Construction: How to Plan Without Slowing the Job Down
New AI Agent Changes Construction Scheduling..Are Schedulers Now Redundant?
Construction Scheduling 101: Complete How-to Guide for Project Managers [2026]
What's New in Planera: April 2026
Planera Releases AI Schedule Assistant; DPR Rolls Out ConstructivIQ on 120+ Projects
Planera Launches Manny, Turning Construction Schedules Into Live Decision Engines
Scheduling Without a Data Date Is Not Just Bad Practice, It's a Liability
Best Microsoft Project Alternatives in 2026 (Top Tools Compared)
July Product Updates: Better bulk actions, Hide collaborator cursors & more
August Product Updates: Four new features + a speed boost you’ll love
September Product Updates: Smarter Permissions, Sharper Insights, Richer Context
October Product Updates: New sorting for P6 imports, flexible IMS, edit-in-Gantt, and more
November Product Updates: Clearer navigation, smarter safeguards, and smoother interactions
December Product Updates: update schedules with confidence, investigate issues faster, and avoid cleanup work
Top 10 Oracle Primavera P6 Alternatives & Competitors for The Construction Industry in 2026
The MS Project Retirement: Why Construction Leaders are Securing Their Future with Planera
February 2026 Product Marketing Update
How to Read and Use a Gantt Chart for Construction Scheduling
Best Construction Workflow Management Software Picked for 2026
11 Best CPM Software of 2026 for Your Construction Project
Building Data Centers Faster and Smarter: Visual, Collaborative Scheduling Isn’t Just an Option—It’s a Business Mandate.
How Big-D Construction uses Planera to avoid ‘death by 1,000 paper cuts’
The Future of Construction Scheduling for GCs to Improve with AI using Planera
13 Best Construction Management Software Platforms to Compare in 2026
From Trailer to Tablet: Making Schedules Work Where the Work Happens
12 Digital Construction Tools Every Contractor Needs in 2026
50 Best Construction Scheduling Software Platforms in 2026
Change Leader: Why Infrastructure Projects Lose Margin Before They Break Ground
Planera Adds Industry Leaders Matt Burness and Mark Baracani to Strengthen Product and Construction Expertise
Planera Expands Data Centre Presence with New Funding
‍Planera Accelerates Data Center Expansion, Raises $8M in New Funding
Miles-McClellan Expands Scheduling with Planera for iPad
Planera September Update: Smarter Permissions, Sharper Insights, Richer Context
AMLI Residential Selects Planera to Transform Project Scheduling and Field Collaboration
The Future is Hybrid: Why Modern Construction Demands both CPM and Lean
The Evolution of Construction Scheduling in the Design-Build Era
Planera Featured on the Art of Construction Podcast
Report: Legacy Tools & Hiring Top Concerns Amid Construction Boom
Sticky Notes Don’t Scale: 5 Reasons to Choose Logic-Driven Scheduling
Drill Tech Selects Planera for Schedule-Critical Tunnel Projects
Scheduling That Keeps Up with Data Center Demands
Bridging the Skills Gap: PlaneraEDU Prepares Digital Jobsite Pros
Watch the Webinar! Planera Field Schedules Linked to Master Plan
Planera Wins 2025 Gold Globee® Award for Disruptors
Planera Launches Collaborative Field Scheduling for Teams
Planera CEO Nitin Bandhari Featured on ENR's Critical Path Podcast
Nitin Bhandari Wins Best Innovative Entrepreneur Award
Not a ‘Shiny Toy’: Contractor Overhauls Scheduling Without Hype
Planera Featured on Construction Conversations Podcast
How Planera Improves Construction Planning with Visual Workflows
Zachry Construction Uses Planera to Optimize Resource Scheduling
Planera Launches Visual, Collaborative Field Scheduling on iPad
Planera Featured on Category Visionaries Podcast
Now Live: Planera on iPad
Planera Featured on AEC Trailblazers: The Founders Files Podcast
Full-Stack Scheduling: Transforming Specialty Contracting Projects